PM’s promise of 100MW solar plant for Gilgit Baltistan fulfilled

*Click the Title above to view complete article on https://www.24newshd.tv/.

2025-08-09T15:00:56+05:00 News Desk

Prime Minister Shehbaz Sharif’s another promise made with the residents of Gilgit-Baltistan, regarding the provision of a 100-megawatt solar photovoltaic power plant, was fulfilled, reported 24NewsHD TV channel.

The Executive Committee of the National Economic Council (ECNEC) approved a 100-megawatt solar photovoltaic power plant project for various locations in Gilgit-Baltistan, two days after the prime minister’s announcement.

Following the ECNEC’s approval, formal work on the project would now kick-start. The project will be completed within three years and cost a total of Rs24.957 billion, PM Office Media Wing, on Saturday, said a press release issued in Islamabad on Saturday.

During his recent visit to Gilgit, the prime minister had announced that ECNEC would soon approve 100-megawatt solar power plant project for Gilgit-Baltistan. The CDWP (Central Development Working Party) had already approved the project earlier.

The districts of Astore, Daryal, Tangir Diamer, Ghanche, Ghizer, Gilgit, Hunza, Ishkoman, Nagar, Rondu, Skardu, and Shigar will benefit from the functioning of the project.

In the first phase, the district of Skardu will be provided with 18.958 megawatts of electricity.

In the second phase, the districts of Hunza, Gilgit, and Diamer will get 6.005 MW, 28.013 MW, and 13.126 MW of electricity respectively.

While in the third phase, the remaining districts will receive 16.096 megawatts of electricity.

The project will also provide 18.162 megawatts off-grid electricity to the hospitals and government offices.

Reporter Awais Kiyani